Total, operator of Block 17, recently announced that the giant Pazflor field offshore Angola has come on stream ahead of the initial schedule

The Pazflor field lies 150km off Luanda in water depths ranging from 600 to 1,200m and has estimated proved and probable reserves of 590mn barrels. The field will gradually ramp up to its full production capacity of 220,000 barrels per day over the coming months.

“Pazflor’s start-up, several weeks ahead of schedule and within budget, is a remarkable achievement of the teams involved. The support and trust of Sonangol, our concession holder and partner, also made an invaluable contribution to our efficiency” says Yves-Louis Darricarrère, President Exploration & Production at Total. “Pazflor required a development effort on the same scale as the field. Paving a way with new technologies, the project showcases Total’s expertise in highly complex environments. The project facilities have been designed and thoroughly tested in accordance with the strictest health, safety and environmental standards. This is another step in the ongoing saga of our deep offshore feats, begun right here in Angola. Deepwater developments are a core driver of our future production growth.”

Total-2011-carte-angola-pazflorVast subsea network

Pazflor comprises a vast subsea gathering network, the most complex ever built in Angola: 180km of lines tying in 49 subsea wells, 10,000 metric tons of subsea equipment and the giant Pazflor floating production, storage and offloading (FPSO) vessel. Held in position by 16 subsea mooring connectors, with its 325m long, 62m wide and a weight of more than 120,000 metric tons, the FPSO is the largest in the world. It can store up to 1.9mn barrels of oil that is then exported to tankers via an offloading buoy. The associated gas is reinjected into the reservoir, but could also be exported to the Angola LNG plant once the latter becomes operational.

A key technical challenge was producing two very different grades of oil from four separate reservoirs. Producing the heavy, viscous oil from the three Miocene reservoirs, which account for two-thirds of the reserves, and the related flow assurance constraints, represented a major challenge. The gas has to be separated from the liquids on the seabed so that the viscous liquids can then be pumped to the surface. The design and installation of subsea gas-liquid separation units and pumps are a world first on this scale. The pumps were purpose designed and tested for Pazflor.

Total’s wholly owned subsidiary Total E&P Angola operates Block 17, with a 40 per cent interest, while Sonangol is the concession holder. The other partners are Statoil ASA (23.3 per cent), Esso Exploration Angola (Block 17) Limited (20 per cent) and BP Exploration (Angola) Ltd (16.67 per cent).

Alain Charles Publishing, University House, 11-13 Lower Grosvenor Place, London, SW1W 0EX, UK
T: +44 20 7834 7676, F: +44 20 7973 0076, W: www.alaincharles.com

twn Are you sure that you want to switch to desktop version?