Total commissions Anguille to Torpille pipelay

 Total Gabon has contracted Sea Trucks to install a 32km (19.9mi) gas pipeline between the Anguille and Torpille fields offshore Gabon

The project includes engineering, procurement, and installation of the 18in. (45.7cm) concrete coated pipeline and associated hardware, diving work, fabrication and installation of spools, and topside modification.

This will be Sea Trucks’ first pipelay project for Total in this part of West Africa. The work will be performed in 2Q 2012, likely using the DP3 vessel Jascon 34.

Alain Charles Publishing, University House, 11-13 Lower Grosvenor Place, London, SW1W 0EX, UK
T: +44 20 7834 7676, F: +44 20 7973 0076, W: www.alaincharles.com